Our lot!

1/12/13 - The hole has been dug and footings poured!

Shane showing Emma!


1/25/13 - Forms going up for the foundation to be poured!

1/31/13 - Foundation has been poured!


2/6/13 - Forms have been removed, now awaiting the trusses to be made.



3/1/13 - Something big is about to happen!
I drove by the house today and took the last picture! The roof trusses still need to arrive, suppose to be here today or Monday. The framers are set to start framing the house on Tuesday! I am starting to get butterflies in my stomach now! The trusses took a little longer than expected, so the construction schedule shows we are a little behind, but my builder said the framers should be able to complete the framing quicker than he projected.